Kedampal Water Project

Kedampal Water Project

Kedampal is a village in a mountains northern of Mount Agung which is 514 families and 2105 people has been struggling for water for years because of the location up in the mountain, there is no water spring, the only water they have is from the raining.

The government building the reservoir its called Embung Datah II , build by government on 2013. This Embung demention is 80mX59mX5m; volume of water 17,682.19 m3 ; length of the water 4,720.00 m3.  Including to Embung Datah II the government also build the pipe to the groups family so they can acces the water, but there is 87 families doesn’t get the acces to the water, this is because the landfield of the mountain so few groups of the families stay up the hill and the must go around to get the water.

For 87 families its need to build the pipe and the water tanks which is need approximately Rp, 113,137,500 or USD $ 7,857

There is 140 families doesn’t have toilet in their house, so there is not enough sanitation for the families. For one Toilet its need approximately Rp, 3,000,000 each Rp, 3,000,000 X 140 = Rp, 420,000,000 about USS$30,000

 

Scope Item Unit Qty Unit cost Cost Unit $ Tot $
Engineering work Lot 1 250,000 250,000 17 17
New Head Tank #7 at Dam (1100 lt) pcs 1 1,500,000 1,500,000 104 104
Headtank Stand Lot 0 250,000 17              –
Group 1 Tank #1 (1100lt) Lot 1 1,500,000 1,500,000 104 104
Group 1 Tank #2 (3300lt) Lot 1 5,000,000 5,000,000 347 347
Group 1 Tank #3 (3300lt) Lot 1 5,000,000 5,000,000 347 347
Group 1 Tank #4 (3300lt) Lot 1 5,000,000 5,000,000 347 347
1.5” pipe from Dam for group 1 tanks #1,2,3, and 4 Pcs 800 69,000 55,200,000 5 3,833
Stage 1 Subtotal 73,450,000             – 5,101
Group 2 Tank #5 (1100lt) pcs 1 1,500,000 1,500,000 104 104
Group 2 pipe 1.0” pcs 210 40,000 8,400,000 3 583
Group 3 tank #6  Tank  (3300 lt) pcs 1 5,000,000 5,000,000 347 347
Group 3 new pipe for tank 1.5” pcs 75 69,000 5,175,000 5 359
Group 3 repair pipe 1.5” pcs 125 69,000 8,625,000 5 599
Fittings, Krank and float valves Lot 7 400,000 2,800,000 28 194
Paint, Glue, Sealant, etc Lot 1 500,000 500,000 35 35
Cement bag 10 70,000 700,000 5 49
Sand truck 0.5 500,000 250,000 35 17
Coral truck 0.5 700,000 350,000 49 24
Misc (petrol, meals, etc for travelling support) Lot 1 1,000,000 1,000,000 69 69
Hygiene Education Program  delivery Lot 0 10,000,000  – 694
Stage 2 Subtotal 34,300,000             – 2,382
Contingency Lot 5% 5,387,500             – 374
Total Rp 113,137,500    $7,857
US$:Rp Exch Rate IDR 14,400      

 

 

 

 